Oil drilling at Kolmani River-II Well to take 60 days — Contractor

The Chief Executive Officer (CEO) of Etihad Oilfield Services Abdulrahman Bashir has said that drilling activities that started at the Kolmani River-II Well over the…

The Chief Executive Officer (CEO) of Etihad Oilfield Services Abdulrahman Bashir has said that drilling activities that started at the Kolmani River-II Well over the weekend will be completed in about 60 days.

Indigenous contractor Messrs Etihad Oilfield Services, a subsidiary of AA&R Investment Group, is the contractor handling drilling operations at the Kolmani River- II Well, a site near Barambu, a village in Alkaleri Local Government Area of Bauchi State.

President Muhammadu Buhari Saturday officially flagged off drilling activities which is expected to confirm the presence of hydrocarbon and the quantity.

The Kolmani River-II Well will be drilled by Ikenga Rig 101 owned by the contractor Etihad Oilfield Sirvices/Drillog Petrodynamics Ltd.

“We are drillers and normally it takes us 60 days to drill a well. In 60 days you can come back and get feedback from NNPC,” the CEO of the company said.

Bashir said the fact that an indigenous service company was handling the project was a testimony that local content is really working.

“We have only three expatriates here not like before when 50 per cent have to be expatriates on this rig. Most of the engineers on the rig are Nigerians,” he said.

Group Managing Director of the NNPC Dr. Maikanti Baru also said the well is designed to be 14,500 feet, deep which would take roughly 60 to 70 days for the NNPC reach its target depth.

“If we reach 14,500 and we still find some interests from the results and it requires that we need to go deeper, this rig is modern, it can go up to 20,000 feet,” he said.

The Kolmani River-II Well is one of four oil and gas wells that NNPC said were being planned for drilling this year on the Gongola Basin to further test the prospects identified around Kolmani River-1, Nasara-1 and Kuzari-1.

Shell had in 1999 drilled the first well in the Kolmani Rever-I but according the Anglo Dutch oil giant the amount of hydrocarbon found was not commercial.

“However, when we read the data, we observed that they did not go deep enough. So, we have come here based on the three dimensional seismic and other subsurface reviews and studies that we have done,”  Baru said.

“At the moment, we are looking at deep down, we are looking at kilometers below the ground, nobody has gone there.  It is only drilling that would confirm whether there is any resource there and  also confirm our professional judgement which we have. So in terms of volumes, types and all that, let us wait.”

LEARN AFFILIATE MARKETING: Learn How to Make Money with Expertnaire Affiliate Marketing Using the Simple 3-Step Method Explained to earn $500-$1000 Per Month.
Click here to learn more.

AMAZON KDP PUBLISHING: Make $1000-$5000+ Monthly Selling Books On Amazon Even If You Are Not A Writer! Using Your Mobile Phone or Laptop.
Click here to learn more.

GHOSTWRITING SERVICES: Learn How to Make Money As a Ghostwriter $1000 or more monthly: Insider Tips to Get Started. Click here to learn more.
Click here to learn more.

SECRET OF EARNING IN CRYPTO: Discover the Secrets of Earning $100 - $2000 Every Week With Crypto & DeFi Jobs.
Click here to learn more.