Fashola to commission 80MVA Yauri substation abandoned for 11yrs

The Minister of Power, Works and Housing, Babatunde Raji Fashola, will this week commission the 80MVA Yauri Transmission Substation in Kebbi State which was abandoned by the contractors after it was started in December, 2007.

The 132/33KV substation completed by the in-house engineers of the Transmission Company of Nigeria (TCN) has two units of 40MVA transformers. While one of the transformers has been energised, the other is being tested and will be energised ahead of the commissioning.

ADVERTISEMENT

For over 11 years, residents of Yauri Emirate, mainly along the River Niger, and hosting the reservoir for Kainji Hydropower dam have decried inadequate power supply in the area.

TCN noted that when it took over the Yauri substation project, installations were only about 50 per cent after the contractor failed to complete it since December, 2007. However, TCN in-house engineers completed the substation within three months.

ADVERTISEMENT

The General Manager, Public Affairs of TCN, Mrs. Ndidi Mbah, said, “The new Yauri 2x40MVA 330/33kV Transmission Substation was first awarded in December, 2007, but the contractor failed persistently to complete the contract for 11 years. Consequently, TCN took over the project in May, 2018, and completed it.”

Download Daily Trust News App

Get it on Google Play

Share this article

BREAKTHROUGH NATURAL CURE FOR PROSTATE ISSUES IN JUST 15 DAYS!!!

You Can Prevent PROSTATE CANCER!!!

Your PROSTATE ENLARGEMENT Is REVERSIBLE!!!

Don't Let It Threaten You!

To SHRINK And NORMALIZE Your PROSTATE Within 15 Days Without Surgery Or Chemical Drugs, Click Here!!!

Join us on


Share your story with us: 08189301900 (Whatsapp and SMS only) Email: dtonline@dailytrust.com

Complain about a story or Report an error and/or correction: +2348189301900

DISCLAIMER: Comments on this thread are that of the maker and they do not necessarily reflect the organizations stand or views on issues.