ADVERTISEMENT

Fashola inspects 215 megawatt Kaduna power plant

The Minister of Power, Works and Housing, Babatunde Raji Fashola on Sunday inspected 215 megawatt Kaduna power plant project.

The minister was taken round the project site by the Project Manager Engineer Sunny Okwedi around 6 pm.

ADVERTISEMENT

The project Manager while briefing the Minister on the progress made so far said the power Control Modules and other equitment were already on site and that work is ongoing without much hitches.

ADVERTISEMENT

He added that the engineering work is 98 percent complete, Procurement 93 percent complete and construction 76 complete.

ADVERTISEMENT

The minister said he was in Kaduna to hold a meeting with some Road controllers and decided to branch to inspect the progress made on the project.

“Although I get reports monthly about the project and the progress made but I feel since I’m here in Kaduna let me come and see for myself and I ‘m satisfied with the progress made” he said.

Dear Esteemed reader,

As part of our drive to keep improving the content of our newspaper, we are conducting a readership survey to enable us serve you better.

Kindly take two minutes of your time to fill in this questionnaire.

Thank you for your time. Click here to begin

Download Daily Trust News App

Get it on Google Play
Share this article

BREAKTHROUGH NATURAL CURE FOR PROSTATE ISSUES IN JUST 15 DAYS!!!

You Can Prevent PROSTATE CANCER!!!

Your PROSTATE ENLARGEMENT Is REVERSIBLE!!!

Don't Let It Threaten You!

To SHRINK And NORMALIZE Your PROSTATE Within 15 Days Without Surgery Or Chemical Drugs, Click Here!!! Order Now! Limited Stock Available!!!

Join us on


Share your story with us: 08189301900 (Whatsapp and SMS only) Email: dtonline@dailytrust.com

Complain about a story or Report an error and/or correction: +2348189301900

DISCLAIMER: Comments on this thread are that of the maker and they do not necessarily reflect the organizations stand or views on issues.