60yrs after: 40mw Dadin-Kowa hydro-power ready for inauguration

The Dadin-Kowa Hydro-Power Plant in Gombe State, initiated in 1959 to generate 40 megawatts of electricity is now ready for inauguration after 60 years of…

The Dadin-Kowa Hydro-Power Plant in Gombe State, initiated in 1959 to generate 40 megawatts of electricity is now ready for inauguration after 60 years of execution setbacks.

Those familiar with the project described it as “a success story” despite the long delay it suffered.

People of Dadin-Kowa and adjoining communities said the power project will add impetus to the socio-economic development of the northern region and the country at large.

Though the project was initiated a year before Nigeria’s independence, the contract for the dam project was not awarded until 1980, and the inauguration eight years later, in 1988, by then military president, General Ibrahim Badamasi Babangida.

The reservoir has a capacity of 800 million cubic meters of water and a surface area of 300 square km.

The dam has potential as a source of fish, but nothing serious was done on the electricity potential until recently.

Governor Muhammadu Inuwa Yahaya of Gombe State with other officials of the plant at the control section of Dadin-Kowa Hydro- Power Plant
Governor Muhammadu Inuwa Yahaya of Gombe State with other officials of the plant at the control section of Dadin-Kowa Hydro- Power Plant

While the dam was inaugurated nearly 40 years ago in 1988,  work on the electricity component, designed to be producing 40 megawatts of electricity, has been going back and forth for 31 years after the dam components had been completed.

The Dadin-Kowa Dam is located 5km north of Dadin- Kowa village and 37km from Gombe town, along Biu road.

LEARN AFFILIATE MARKETING: Learn How to Make Money with Expertnaire Affiliate Marketing Using the Simple 3-Step Method Explained to earn $500-$1000 Per Month.
Click here to learn more.

AMAZON KDP PUBLISHING: Make $1000-$5000+ Monthly Selling Books On Amazon Even If You Are Not A Writer! Using Your Mobile Phone or Laptop.
Click here to learn more.

GHOSTWRITING SERVICES: Learn How to Make Money As a Ghostwriter $1000 or more monthly: Insider Tips to Get Started. Click here to learn more.
Click here to learn more.

SECRET OF EARNING IN CRYPTO: Discover the Secrets of Earning $100 - $2000 Every Week With Crypto & DeFi Jobs.
Click here to learn more.